Status Updates

The last update was on 22-12-2022

S.NO Project Name Status
1 EXTENSION OF THE EXISTING CONTAINER TERMINAL ON DBFOT BASIS (VCTPL PHASE 2) Container terminal is in operation
2 IMPROVING THE CAPACITY UTILISATION OF OR-1&11 BERTHS IN INNER HARBOUR OF VISAKHAPATNAM PORT
  • Physical Progress is 65%.
  • Dredging work is in progress
3 DEVELOPMENT OF CRUISE BERTH & TERMINAL FOR CRUISE TOURISM AT CHANNEL BERTH OF VPA
  • BERTH: Physical Progress 32% completed against 56%.
  • TERMINAL BUILDING: Physical Progress 31% completed against 46%.
4 CONSTRUCTION OF COVERED STORAGE SHED IN PORT AREA OF SIZE 400 X 40 X 17M @ R-11 AREA
  • SHED at R2: M/S. J.D. Constructions have submitted the Designs.
  • SHED at Rll Work is under progress by M/S. PJR Constructions
5 MECHANIZATION OF WQ-7&8 BERTHS FOR MULTIPLE CARGOES Date of Completion of construction — April 2025 (likely)
6 MECHANIZATION OF EQ-7 BERTH FOR MULTIPLE CARGOES Date of Completion of construction — April 2025 (likely)