Sl.No. Name of Project Total Cost of Project (In Cr.) Remarks
1 Improving the capacity utilization of OR- 1and OR-2 berths (Construction of OR-I, OR-II & OR-III berths) 167.66
  • Phase-I: OR-III berth work completed on 10.07.2020 and commissioned on 16.02.2021.
  • Phase-II: OR-I berth work completed and inaugurated on 04.09.23 & operations commenced on 07.10.2023.
  • Phase-III: Deck slab and foundation, dredging work is in progress
  • Physical Progress: 78.04%
2 Construction of covered storage shed No. 3 of size 200x40x17m at R-10 area in Port. 22.50
  • Work is in progress.
  • Physical Progress: 55.68%
3 Rehabilitation of Deck structure of Sardar Vallabhai Patel bridge (Parallel bridge). 25.90
  • Work is in progress.
  • Bridge handed over to the Contractor from 01.04.2024 ,but due to technical issue the road bridge opened again as per the instructions of ADCP.
  • Physical Progress: 49.00%
4 Modernization & up gradation of Fishing Harbour at Visakha-patnam Port - Phase-I 37.26
  • Net Mending Building painting works, Packing unit & cold chamber Brick masonry works and plastering works, Parking area slab works, Road & drainage works and Gate complex works under progress.
  • Physical Progress: 57.00%
5 Modernization & upgradation of Fishing Harbour at Visakha-patnam Port - Phase III 32.86
  • Work order issued to M/s. Shrushti Contech Pvt. Ltd. on 24.04.2023.
  • Existing Lessee has been vacated and the foundation works for Auction Hall-02 commenced on 19.12.23 and is in progress.
  • Physical Progress: 9.75%
6 Modernization & upgradation of Fishing Harbour at Visakhapatnam Port - ETP’s - Phase IV 5.27
  • Work order issued to M/s. Aquachem Enviro Engineers Pvt. Ltd., on 24.08.2023 for an amount of Rs.5.27 Cr.
  • Work was commenced on 07.09.2023 & is in progress
  • Physical Progress: 66.00%
7 Improvement of Visakhapatnam Railway tracks & rectification of sharp curves more than 10 degrees 21.69
  • IPRCL has been procuring the 60 Kg Rails, sleepers etc.
  • Physical Progress: 50.30%
8 Up-gradation of East yard railway tracks in VPA 17.03
  • Procurement of material is in progress.
  • Physical Progress: 49.80%
9 Modernization & upgradation of Fishing Harbour at Visakhapatnam Port – Dredging Work – Phase-VI 5.92
  • Work order issued on 29.01.2024.
  • The work has been commenced on 16.02.2024 and mobilization is in progress.
10 Modernization and up gradation of Fishing Harbour at Visakhapatnam Port - Supply, Installation, Commissioning and Testing of Floating Jetty – Phase-V 9.49
  • The Bid opened on 04.05.2023 (3rd call) and no one participated.
  • Fishermen requested for permanent jetty instead of Floating Jetty.
  • A letter has been addressed to the Secretary, MoPSW & Ministry of Fisheries on 26.09.2023 for revised scope of work.
11 Construction of two additional breasting dolphins (BD-3 and BD-4) to accommodate medium range vessels at OSTT of Visakhapatnam Port. 18.63
  • NIT issued on 05.02.2024.
  • Bids opened on 07.03.2024 & evaluation completed.
  • Note processed to accord sanction to open the price bid.
12 Repairs to the pockets along the SL canal Jetty and Backup area to avoid erosion of bund (berthing area for Port crafts) 14.48
  • NIT issued on 26.04.2024.
  • Bid opening Date 29.05.2024
13 Providing New Fire Fighting Facilities suitable to the upgrading capacities of Berths OR-l & ll to accommodate 50,000 to 1,00,000 DWT Vessels (Panamax Vessels) as per OISD 156 guidelines in a phased manner- Phase-I 4.22 The existing Fire Fighting Facilities are suitable for handling vessels of Capacity up to 50,000 DWT. Hence the Fire Fighting Facilities are enhancing to accommodate the Vessels of capacity 50,000 to 1,00,000 DWT.
14 Providing New Fire Fighting Facilities suitable to the upgrading capacities of Berths OR-l & ll to accommodate 50,000 to 1,00,000 DWT Vessels (Panamax Vessels) as per OISD 156 guidelines in a phased manner- Phase-II 27.13 The existing Fire Fighting Facilities are suitable for handling vessels of Capacity up to 50,000 DWT. Hence the Fire Fighting Facilities are enhancing to accommodate the Vessels of capacity 50,000 to 1,00,000 DWT.
15 Up-gradation of Fire Fighting Facilities for OSTT Berth to accommodate Vessels of capacity 1,00,000 DWT and above (Cape size Vessels) as per OISD 156 guidelines including Annual Maintenance Contract (AMC) for 10 (ten) years for Operations and Maintenance ( O & M ) of Upgraded Fire Fighting Facilities of OSTT”. 28.59 The existing Fire Fighting Facilities are suitable for handling vessels of Capacity up to 50,000 DWT. Hence the Fire Fighting Facilities are enhancing to accommodate the Vessels of capacity above 1,00,000 DWT.
16 Mechanization of WQ-7 & 8 Berths at Visakhapatnam Port 288.47 VPT Envisaged to develop WQ-7 & WQ-8 Berths by provding mechanized handling facilities to handle bulk cargoes. These berths were constructed with internal resources at a cost of Rs, 243/- Crores. Total legth of the Berth is 560 mtrs. Capacity 6.14 MTPA.
17 Mechanization of EQ-7 Berth at Visakhapatnam Port. 200.99 VPT Envisaged to develop EQ-7 Berth by provding mechanized handling facilities to handle multiple cargoes including fertilizers. Total legth of the Berth is 255 mtrs. Capacity 3.61 MTPA.
18 Smart Port Surveillance using AI & VA for Port shipping Railway operation. 25 Cr. In order to improve operational efficiency in VPA like ship arrivals, ship departures, Idle Hours, Berth occupancy, Berth utilitiesation, similarly detection & Pointing alerts while congestion at gates, Tarpoulin Coverage of coal stacks, unmanned Railway crossing etc.
19 Extension of Port Custom bound area by providing new gates Infrastructure. 1.40Lacs Improving Vehicle movement, better connectivity to storage area, reduce vehicle congestion, smooth road traffic to evacuate Cargo faster.
20 PMC work for development of 33/11 KV outdoor Substation at VPA. 0.37Cr. Work order awarded to M/s PTC India Ltd., New Delhi
21 Electrification of 38 TKM Railways lines in 3 phases. 21.09 Work order awarded to M/s IPRCL, Visakhapatnam.
22 Operational & Maintenance of EQ1 terminal. 42.44 Work order awarded to M/s HIQ services and feedback power operation and maintenance services private ltd.
PROPOSAL STAGE WORKS
  • Rehabilitation of Jetty No’s- 1,2,3,4,Wet Basin & DC Jetty in the Entrance Channel of Visakhapatnam Port
  • deepening of the Entrance Channel & Inner Harbour and Strengthening of existing berths in Visakhapatnam Port
  • Rehabilitation of Fertilizers Berth for Higher Draft Vessels in the North-Western Arm of Inner Harbour of Visakhapatanm Port